NMS-002 · Automotive · Flagship · Global · 47 markets

Apex EV Launch

at-risk
T-minus
180 days
Current gate
G4 · Proto 1
Budget
$28.0M / $35.0M
Launch
2026-10-22
Program
NMS-002 · Apex EV Launch
Current gate
G4 · Prototype 1
Critical path
Engineering lane
Projected slip
+56 days
Original target
Oct 22, 2026
Projected launch (with delays)
Dec 17, 2026
NMS-002 kickoff— slip 56d →
Swim lane
Gate 1
Program Inception
Gate 2
Concept Review (PCR)
Gate 3
Engineering Review
Gate 4
Prototype 1
Gate 5
Prototype 2
Gate 6
Mass Production
Design
63% complete
idle
idle
Finance
60% complete
Battery cell cost overrun
idle
idle
Operations
62% complete
idle
idle
Installation
59% complete
idle
idle
EngineeringCritical Path
55% complete
Powertrain validation failure on cold-weather cycle
idle
idle
ReadyAt RiskBlockedCritical path lane