Timeline

Planned vs projected. Day by day.

Pick a program to see its Gantt schedule — original plan against the currently projected dates, gate sign-off markers, and external milestones.

Original launch
Sep 12, 2026
Projected launch
Sep 26, 2026
Total days slipped
+14 days
Cost variance (all lanes)
+$0.95M

Gantt — Planned vs Projected

Swim lane
Oct '25Nov '25Dec '25Jan '26Feb '26Mar '26Apr '26May '26Jun '26Jul '26Aug '26Sep '26Oct '26Nov '26Dec '26
Cost var
Design
+7d slip
+$90k
Finance
+7d slip
+$480k
Operations
+14d slip
+$448k
Installation
+14d slip
+$320k
Engineering
+9d slip
+$60k
Gate sign-off
Milestones
Retail floor set
EMEA buyer preview
Today