Consequences engine

Cost & timeline cascade

Pick a program to see how each at-risk swim lane cascades into downstream cost and timeline impacts across the other teams.

Cascading delay (peak)
14d
Across downstream lanes
Cost cascade (total)
$0.95M
Forecast variance to budget
Active consequences
4
Live cascade links

Cascade Map

Source → Target
  • G2
    Operations
    source
    G3
    Installation
    target
    +14d+$320khigh

    Vendor SLA gap pushes pilot fixture delivery into G3 window.

  • G2
    Operations
    source
    G3
    Finance
    target
    +0d+$480khigh

    Expedited freight to recover schedule adds line-item cost.

  • G2
    Finance
    source
    G3
    Design
    target
    +7d+$90kmed

    Tariff revision forces material respec on 2 SKUs.

  • G2
    Operations
    source
    G3
    Engineering
    target
    +9d+$60kmed

    POS firmware integration window shifts right.

Impact by Team

Design
$90k
+7d schedule slip
Finance
$480k
+0d schedule slip
Operations
Clear
No impact
Installation
$320k
+14d schedule slip
Engineering
$60k
+9d schedule slip