NMS-001 · Footwear · Flagship · EMEA · 42 stores
Atlas FW26 Flagship
at-risk
T-minus
142 days
Current gate
G2 · PCR
Budget
$9.2M / $18.4M
Launch
2026-09-12
Program
NMS-001 · Atlas FW26 Flagship
Current gate
G2 · Concept Review (PCR)
Critical path
Operations lane
Projected slip
+14 days
Original target
Sep 12, 2026
Projected launch (with delays)
Sep 26, 2026
NMS-001 kickoff— slip 14d →
Swim lane
Gate 1
Program Inception
Gate 2
Concept Review (PCR)
Gate 3
Engineering Review
Gate 4
Prototype 1
Gate 5
Prototype 2
Gate 6
Mass Production
Design
29% complete
idle—
idle—
idle—
idle—
Finance
25% complete
Tariff revision pending
idle—
idle—
idle—
idle—
OperationsCritical Path
20% complete
Vendor SLA unsigned
idle—
idle—
idle—
idle—
Installation
23% complete
idle—
idle—
idle—
idle—
Engineering
26% complete
idle—
idle—
idle—
idle—
ReadyAt RiskBlockedCritical path lane