NMS-004 · Retail · Flagship · Global · 847 stores

Summit Display — Global Retail Launch

at-risk
T-minus
210 days
Current gate
G3 · Eng Review
Budget
$12.4M / $18.0M
Launch
2026-11-21
Program
NMS-004 · Summit Display — Global Retail Launch
Current gate
G3 · Engineering Review
Critical path
Installation lane
Projected slip
+91 days
Original target
Nov 21, 2026
Projected launch (with delays)
Feb 20, 2027
NMS-004 kickoff— slip 91d →
Swim lane
Gate 1
Program Inception
Gate 2
Concept Review (PCR)
Gate 3
Engineering Review
Gate 4
Prototype 1
Gate 5
Prototype 2
Gate 6
Mass Production
Design
50% complete
idle
idle
idle
Finance
50% complete
idle
idle
idle
Operations
45% complete
idle
idle
idle
InstallationCritical Path
36% complete
Fixture certification gap
idle
idle
idle
Engineering
44% complete
idle
idle
idle
ReadyAt RiskBlockedCritical path lane